Industry Briefing

Reducing Interface Risk in Multi-Contractor Projects

How PMC governance creates clarity and accountability across complex delivery ecosystems

By XSAT Project Management Team
Reading time: 18 min

Executive Summary

Large-scale oil and gas projects routinely involve 10-20 contractors working simultaneously across engineering, procurement, construction, and commissioning phases. Each contractor boundary represents a potential interface failure - a gap where responsibility becomes ambiguous, deliverables misalign, or critical information fails to transfer. Industry data suggests that interface-related issues account for 30-40% of project delays and cost overruns.

Project Management Consultants (PMCs) exist precisely to manage this complexity. Effective PMC governance transforms interface management from reactive firefighting into proactive risk mitigation. This briefing examines the mechanisms through which PMCs establish clarity, enforce accountability, and reduce interface risk across complex delivery ecosystems.

The Interface Risk Challenge

What Are Project Interfaces?

Interfaces exist wherever work packages, systems, or organizations meet. In multi-contractor projects, interfaces manifest in multiple dimensions:

  • Physical Interfaces: Where one contractor's equipment connects to another's (e.g., SCADA system integrating with third-party flow meters, electrical substations feeding process equipment).
  • Functional Interfaces: Where one contractor's deliverable depends on another's output (e.g., civil foundations designed to support mechanical equipment, control logic requiring instrument specifications).
  • Organizational Interfaces: Where responsibilities transition between contractors (e.g., equipment handover from fabricator to installer, commissioning responsibility transfer from EPC to operations).
  • Temporal Interfaces: Where work sequencing creates dependencies (e.g., electrical installation cannot proceed until mechanical equipment is set, software configuration requires hardware commissioning).

Why Interfaces Fail

Interface failures stem from predictable root causes:

  • Ambiguous Responsibility: Contractors assume the other party owns the interface. Classic example: "We deliver the cable; they provide the termination" - but neither party clarifies connector specifications, resulting in incompatible hardware on-site.
  • Information Gaps: Critical design parameters fail to transfer between contractors. The instrumentation vendor doesn't receive updated process conditions from the process engineer, leading to undersized instruments.
  • Assumption Mismatches: Each contractor makes different assumptions about shared boundaries. The civil contractor assumes equipment foundations include anchor bolts; the mechanical contractor expects to supply them. Both assumptions are documented - but in separate, unreconciled documents.
  • Change Management Breakdown: Design changes propagate through one contractor's scope but fail to reach dependent contractors. A pipe routing change invalidates the cable tray layout, discovered only during installation.
  • Contractual Gaps: Contracts define each contractor's scope but leave interface activities undefined. Neither contractor is contractually obligated to coordinate, so coordination doesn't happen.

The Cost of Interface Failures

Interface failures manifest as rework, delays, and claims:

  • Rework: Incompatible equipment requires modification or replacement. A SCADA system designed for Modbus communication arrives at a site where all RTUs use DNP3 protocol - requiring costly protocol converters or RTU replacement.
  • Schedule Delays: Missing interface deliverables stall downstream work. Electrical contractors mobilize to site but cannot proceed because mechanical equipment (which provides mounting points for electrical panels) hasn't been installed.
  • Claims and Disputes: Contractors dispute responsibility for interface failures, triggering contractual claims that consume management attention and legal fees.
  • Safety Incidents: In worst cases, interface failures create safety hazards. Mismatched electrical ratings, incorrect valve actuation logic, or inadequate grounding can endanger personnel and equipment.

A 2023 industry survey of major oil and gas projects found that interface-related issues contributed to:

  • 35% average schedule overrun on projects with weak interface governance
  • 28% average cost overrun attributed to rework and claims
  • 60% of commissioning delays traced to unresolved interface issues

PMC Governance Framework

Effective PMCs establish governance frameworks that systematically identify, document, manage, and close out interfaces. This framework operates across four pillars: organizational structure, processes and tools, contractual mechanisms, and cultural norms.

Pillar 1: Organizational Structure

Interface Management Team

The PMC establishes a dedicated interface management function, typically led by an Interface Manager reporting directly to the Project Director. For large projects (>$500M), this may be a full-time team of 3-5 specialists. Smaller projects assign interface management as a secondary responsibility to discipline leads.

Interface Manager Responsibilities
  • Maintain the Interface Register (master database of all project interfaces)
  • Chair Interface Coordination Meetings with all contractors
  • Audit interface deliverables for completeness and consistency
  • Escalate unresolved interface issues to Project Director
  • Report interface risk metrics to Owner and governance boards

Interface Coordinators

Each major contractor designates an Interface Coordinator as the single point of contact for interface matters. This individual attends PMC-led coordination meetings, commits their organization to interface agreements, and ensures internal follow-through.

Critical Success Factor: Interface Coordinators must have authority to commit their organization. A junior engineer attending coordination meetings but lacking decision-making power creates a bottleneck that defeats the purpose of coordination.

RACI Matrix for Interface Governance

Table 1: RACI Matrix for Interface Governance
ActivityPMCContractor AContractor BOwner
Identify interfacesRCCI
Document interface requirementsARRC
Approve Interface Control DocumentsACCI
Resolve interface conflictsARRC
Audit interface deliverablesRIIA
Close out interfacesARRI

Key Principle: The PMC is Accountable for interface management but not Responsible for executing interface work - that responsibility lies with contractors. The PMC ensures interfaces are managed; contractors ensure interfaces are delivered.

Pillar 2: Processes and Tools

Interface Register

The Interface Register is the single source of truth for all project interfaces. It catalogs every interface, assigns ownership, tracks status, and flags risks.

Typical Interface Register Fields
  • Interface ID: Unique identifier (e.g., IF-001, IF-002)
  • Interface Type: Physical, Functional, Organizational, Temporal
  • Parties: Which contractors/disciplines are involved
  • Description: Brief description of the interface
  • Status: Identified, Agreed, In Progress, Closed
  • Owner: Which contractor is responsible for delivering the interface
  • Dependent Party: Which contractor depends on the interface
  • Risk Level: Low, Medium, High, Critical
  • Due Date: When the interface must be resolved
  • ICD Reference: Link to detailed documentation
Example Interface Register Entry
IDTypePartiesDescriptionStatusOwnerDependentRiskDue DateICD Ref
IF-023PhysicalEPC-A / SCADA IntegratorSCADA system connection to EPC-A DCS via OPC UAIn ProgressSCADA IntegratorEPC-AHigh2025-06-15ICD-023

The Interface Register is a living document, updated weekly during active project phases. The PMC reviews the register in every coordination meeting, highlighting new interfaces, status changes, and overdue items.

Interface Control Documents (ICDs)

For complex or high-risk interfaces, the PMC requires detailed Interface Control Documents. ICDs formalize the technical and organizational agreement between parties.

  1. Interface Description: What is being interfaced (systems, equipment, data)
  2. Parties and Responsibilities: Who delivers what, using RACI format
  3. Technical Specifications: Detailed requirements (protocols, voltages, mechanical connections, data formats)
  4. Interface Points: Physical locations or logical boundaries where interface occurs
  5. Deliverables: Documents, drawings, equipment, or data that must be exchanged
  6. Schedule: Milestones and dependencies
  7. Acceptance Criteria: How interface completion will be verified
  8. Change Management: Process for handling interface changes
  9. Escalation Path: Who resolves disputes if parties cannot agree
Example: SCADA-to-DCS Interface Control Document

Interface ID: IF-023

Parties: SCADA Integrator (Party A) / EPC-A (Party B)

Interface Description: Real-time data exchange between SCADA supervisory system and EPC-A Distributed Control System (DCS) for process monitoring and control.

Technical Specifications
  • Protocol: OPC UA (IEC 62541)
  • Network: Dedicated VLAN on plant Ethernet (10.50.0.0/24)
  • Data Points: 1,200 tags (analog inputs, digital inputs, setpoints)
  • Update Rate: 1-second for critical tags, 5-second for non-critical
  • Security: TLS 1.3 encryption, certificate-based authentication
  • Redundancy: Dual OPC UA servers (primary/standby) on DCS side
Responsibilities (RACI)
ActivitySCADA IntegratorEPC-APMC
Define tag listCRA
Configure OPC UA serverIRI
Configure OPC UA clientRCI
Network infrastructureIRI
Integration testingRRA
Security certificatesRRC
Deliverables
  • Party B: Tag list (Excel), OPC UA server configuration, network diagram
  • Party A: OPC UA client configuration, test procedures, test results
Schedule
  • Tag list finalized: 2025-05-01
  • OPC UA server commissioned: 2025-05-20
  • Integration testing complete: 2025-06-10
  • Interface closed: 2025-06-15
Acceptance Criteria
  • All 1,200 tags transmit successfully with <1% packet loss
  • Update rates meet specification under full load
  • Failover to standby server completes within 5 seconds
  • Security scan shows no vulnerabilities (CVSS score <4.0)

Change Management: Any changes to tag list, protocol, or network configuration require written approval from both Interface Coordinators and PMC Interface Manager.

Escalation Path: Unresolved technical disputes escalate to PMC Engineering Manager within 48 hours. Contractual disputes escalate to PMC Project Director.

Signatures: SCADA Integrator Interface Coordinator, EPC-A Interface Coordinator, PMC Interface Manager.

Interface Coordination Meetings

The PMC chairs regular Interface Coordination Meetings (typically bi-weekly during design/construction, weekly during commissioning). These meetings review interface status, resolve issues, and assign actions.

Meeting Agenda
  1. Review Interface Register: new interfaces, status updates, overdue items
  2. Discuss high-risk interfaces: technical challenges, schedule conflicts
  3. Review pending ICDs: approve new ICDs, update existing ones
  4. Action item review: follow up on previous meeting commitments
  5. Look-ahead: upcoming interfaces requiring attention
Meeting Outputs
  • Updated Interface Register
  • Action Item Log with assigned owners and due dates
  • Meeting minutes distributed within 24 hours

Critical Success Factor: Interface meetings must be decision-making forums, not information-sharing sessions. Interface Coordinators attend with authority to commit their organizations. Decisions made in meetings are binding; revisiting decisions outside meetings is discouraged unless new information emerges.

Interface Risk Register

High-risk interfaces receive special attention through an Interface Risk Register, a subset of the project risk register focused specifically on interface-related risks.

Example Interface Risk Entry
  • Risk ID: IR-005
  • Interface: SCADA-to-DCS integration (IF-023)
  • Risk Description: OPC UA protocol version mismatch between SCADA client and DCS server may prevent communication.
  • Probability: Medium (30%)
  • Impact: High (3-week commissioning delay, $500K cost impact)
  • Risk Score: 15 (Medium-High)
Mitigation Actions
  1. Verify OPC UA version compatibility in design phase (Owner: SCADA Integrator, Due: 2025-04-15)
  2. Conduct early integration test with sample tags (Owner: PMC, Due: 2025-05-01)
  3. Procure protocol gateway as contingency (Owner: PMC, Due: 2025-05-10)

Status: Mitigation in progress

The PMC reviews the Interface Risk Register monthly with the Owner and escalates critical risks to the project steering committee.

Pillar 3: Contractual Mechanisms

The PMC ensures that all contractor agreements include explicit interface management clauses. These clauses define contractors' obligations to participate in interface coordination, deliver interface documentation, and resolve interface issues.

Interface Clauses in Contractor Agreements

Standard Interface Clause Language

The Contractor shall participate in the Project Management Consultant's Interface Management process, including but not limited to:

  • Designating an Interface Coordinator with authority to commit the Contractor
  • Attending Interface Coordination Meetings as scheduled by the PMC
  • Identifying and documenting all interfaces with other Contractors' work
  • Preparing and agreeing Interface Control Documents for interfaces within Contractor's scope
  • Delivering interface-related information, drawings, and specifications as required by ICDs
  • Resolving interface issues in good faith and in a timely manner
  • Notifying the PMC immediately of any interface risks or conflicts

The Contractor acknowledges that failure to fulfill interface management obligations may result in delays, additional costs, or scope changes for which the Contractor may be held liable.

This contractual language transforms interface management from a voluntary coordination activity into a binding obligation.

Interface Agreements Between Contractors

For critical interfaces, the PMC facilitates direct Interface Agreements between contractors. These agreements supplement the ICD with contractual commitments.

  1. Parties: Contractor A and Contractor B
  2. Interface Scope: Reference to ICD
  3. Commitments: Specific deliverables, dates, and quality standards
  4. Liability: How interface failures will be addressed (e.g., responsible party bears rework costs)
  5. Dispute Resolution: Process for resolving disagreements (escalation to PMC, then Owner)
  6. Signatures: Authorized representatives from both contractors

Interface Agreements create peer-to-peer accountability, reducing reliance on PMC enforcement.

Incentive Alignment

Progressive Owners and PMCs structure contractor incentives to reward interface performance. Examples include:

Interface Performance Metrics: Contractors earn bonus payments based on percentage of interfaces closed on schedule, number of interface-related NCRs (Non-Conformance Reports), and responsiveness to interface coordination requests.

Shared Risk/Reward Pools: Multiple contractors share a performance bonus pool. If any contractor's interface failures delay the project, the entire pool is reduced - creating peer pressure for interface discipline.

Early Completion Bonuses: Contractors who close interfaces ahead of schedule receive accelerated payments or bonus fees, incentivizing proactive coordination.

Pillar 4: Cultural Norms

Contractual mechanisms and processes provide structure, but culture determines whether interface management succeeds.

Collaborative Mindset

The PMC cultivates a collaborative mindset through several practices:

  • Joint Problem-Solving: When interface issues arise, the PMC frames them as shared problems requiring joint solutions, not opportunities to assign blame.
  • Transparency: The PMC encourages contractors to surface interface risks early, without fear of penalty. A contractor who identifies a potential conflict in design phase receives recognition, not criticism.
  • Shared Success: The PMC celebrates interface milestones - when a complex interface closes successfully, all parties receive acknowledgment in project communications.

No-Blame Interface Reviews

After commissioning, the PMC conducts a No-Blame Interface Review - a lessons-learned session focused on understanding what worked, what didn't, and how to improve future projects. Contractors participate openly because the review explicitly excludes contractual liability discussions.

Review Questions
  • Which interfaces were most challenging? Why?
  • Where did our interface management process succeed or fail?
  • What information was missing or arrived too late?
  • How can we improve interface identification and documentation?
  • What tools or techniques should we adopt for future projects?

Case Study: Multi-Contractor LNG Plant

To illustrate PMC interface governance in practice, consider a $2.5B LNG (Liquefied Natural Gas) plant project involving seven major contractors:

Project Context

  • EPC Contractor A: Process units (liquefaction, refrigeration)
  • EPC Contractor B: Utilities and offsites (power generation, water treatment)
  • SCADA Integrator: Control system integration across all units
  • Electrical Contractor: Substation and distribution
  • Civil Contractor: Foundations, structures, roads
  • Marine Contractor: Jetty and loading facilities
  • Commissioning Contractor: Startup and performance testing

Interface Challenges

  • 150+ identified interfaces across seven contractors
  • Critical path dependencies: SCADA system required inputs from both EPC contractors, electrical contractor, and marine contractor
  • Geographic dispersion: Contractors based in five countries, equipment fabricated in eight countries
  • Tight schedule: 36-month EPC duration with no float for interface delays

PMC Governance Implementation

Organizational Structure:

  • Full-time Interface Manager and two Interface Engineers
  • Each contractor designated Interface Coordinator and backup
  • Weekly Interface Coordination Meetings (mandatory attendance)
  • Monthly Interface Risk Review with Owner

Processes and Tools:

  • Interface Register maintained in SharePoint with real-time updates
  • 45 Interface Control Documents prepared for high-risk interfaces
  • Interface Risk Register tracked 20 critical interface risks
  • Automated email alerts when interfaces became overdue

Contractual Mechanisms:

  • All contractor agreements included interface management clause
  • 12 Interface Agreements executed between contractors for critical interfaces
  • Performance incentives: 5% of contractor fee tied to interface metrics

Cultural Initiatives:

  • Quarterly "Interface Excellence Awards" recognizing contractors with best interface performance
  • Open-door policy: contractors could escalate interface concerns directly to PMC Project Director
  • No-blame culture: early identification of interface risks rewarded, not penalized

Outcomes

Interface Performance:

  • 148 of 150 interfaces closed on or ahead of schedule (98.7% on-time closure rate)
  • 2 interfaces delayed (both resolved within 1 week)
  • Zero interface-related claims or disputes between contractors
  • All 20 critical risks mitigated successfully

Project Performance:

  • Project completed 2 months ahead of schedule (attributed partly to effective interface management)
  • Cost performance: 3% under budget
  • Commissioning duration: 20% shorter than industry benchmark (due to pre-resolved interfaces)

Lessons Learned:

  • Early interface identification (during FEED phase) prevented 80% of potential interface conflicts
  • Interface Agreements between contractors reduced PMC enforcement burden
  • Weekly coordination meetings (vs. bi-weekly) were essential during construction phase
  • Automated alerts prevented interfaces from falling through cracks

Practical Recommendations for PMCs

Based on field experience across dozens of multi-contractor projects, the following recommendations enhance PMC interface governance effectiveness:

1. Start Early

Interface management begins in the Front-End Engineering Design (FEED) phase, not when construction starts. Early identification allows interfaces to be designed out (through scope clarification) or designed in (through explicit interface specifications) before contracts are awarded.

Action: Conduct an Interface Identification Workshop during FEED, bringing together Owner, PMC, and key contractors (if already selected) to brainstorm potential interfaces.

2. Assign Clear Ownership

Every interface must have a designated Owner - the contractor responsible for delivering the interface. Avoid shared ownership or joint responsibility, which diffuses accountability.

Action: For each interface, ask "Who delivers the physical connection, document, or deliverable?" That party is the Owner. The other party is the Dependent Party who receives or relies on the interface.

3. Prioritize Ruthlessly

Not all interfaces are equally critical. Focus PMC resources (detailed ICDs, frequent reviews, escalation attention) on high-risk interfaces. Low-risk interfaces can be managed with lighter-touch coordination.

Risk Criteria
  • Technical Complexity: Novel technology, tight tolerances, or multiple dependencies
  • Schedule Criticality: Interfaces on the critical path or with no float
  • Cost Impact: Interfaces where failure would trigger expensive rework
  • Safety Implications: Interfaces affecting process safety or personnel safety

Action: Classify interfaces as Critical, High, Medium, or Low risk. Require ICDs for Critical and High interfaces; manage Medium and Low interfaces through the Interface Register alone.

4. Enforce Discipline

Interface management only works if contractors comply. The PMC must enforce interface obligations through:

  • Regular Audits: Review contractor deliverables for interface compliance (e.g., "Did the electrical contractor provide cable schedules to the SCADA integrator as required by ICD-015?").
  • Escalation: When contractors fail to meet interface commitments, escalate promptly - first to the contractor's project manager, then to senior management, and finally to the Owner for contractual action.
  • Visibility: Publish interface performance metrics (e.g., percentage of interfaces closed on time by contractor). Peer visibility creates accountability.

5. Facilitate, Don't Dictate

The PMC's role is to facilitate coordination, not to design interfaces or dictate technical solutions. Contractors possess the technical expertise; the PMC ensures that expertise is applied to interface resolution.

Action: In Interface Coordination Meetings, the PMC asks "What do you need from each other to close this interface?" rather than "Here's how you should close this interface."

6. Document Everything

Interface management generates significant documentation: registers, ICDs, meeting minutes, agreements. This documentation serves multiple purposes:

  • Operational: Provides reference for contractors executing interface work.
  • Audit Trail: Demonstrates due diligence if interface disputes arise.
  • Lessons Learned: Informs future projects about what worked and what didn't.

Action: Use a centralized document management system (SharePoint, Aconex, Procore) where all interface documentation is stored, versioned, and accessible to all parties.

7. Close Interfaces Formally

An interface is not done until both parties agree it's closed and the PMC verifies closure. Formal closure prevents interfaces from reopening during commissioning.

Closure Criteria
  • All deliverables specified in the ICD have been delivered
  • Dependent party confirms deliverables are acceptable
  • Physical interfaces have been tested and verified
  • Documentation is complete and archived

Action: Require both parties to sign an Interface Closure Certificate before removing the interface from the active register.

Common Pitfalls and How to Avoid Them

Pitfall 1: Late Interface Identification

Symptom: Interfaces discovered during construction or commissioning, when resolution is expensive and disruptive.

Root Cause: Interface identification treated as a one-time activity during project kickoff, rather than a continuous process.

Solution: Conduct interface identification workshops at every project phase (FEED, detailed design, procurement, construction, commissioning). New interfaces emerge as designs mature and contractors join the project.

Pitfall 2: Interface Coordinator Lacks Authority

Symptom: Interface Coordinators attend meetings, take notes, but cannot commit their organizations. Decisions require approval from management, causing delays.

Root Cause: Contractors assign junior staff to the interface coordination role to minimize cost.

Solution: PMC contractually requires Interface Coordinators to have decision-making authority. If a contractor's coordinator cannot commit, the PMC escalates to the contractor's project manager and requests a replacement.

Pitfall 3: ICDs Become Shelfware

Symptom: Detailed ICDs are prepared, signed, and filed - but contractors don't follow them. Interface failures occur despite documented agreements.

Root Cause: ICDs are treated as compliance documents rather than working tools.

Solution: Reference ICDs actively in coordination meetings. When interface issues arise, the PMC asks "What does the ICD say?" and holds parties accountable to their documented commitments. ICDs should be living documents, updated as designs evolve.

Pitfall 4: No Escalation Path

Symptom: Interface conflicts linger unresolved because contractors cannot agree, and no one has authority to force a decision.

Root Cause: Escalation paths undefined or unclear.

Solution: Every ICD includes a clear escalation path (typically: Interface Coordinators -> PMC Interface Manager -> PMC Project Director -> Owner). Set time limits for escalation (e.g., "If Interface Coordinators cannot resolve within 5 business days, issue escalates to PMC Interface Manager").

Pitfall 5: Interface Management Stops After Design

Symptom: Interface management is rigorous during design phase but relaxes during construction and commissioning, leading to late-stage surprises.

Root Cause: PMC assumes that once interfaces are designed and documented, they will execute automatically.

Solution: Interface management continues through commissioning. The PMC audits interface execution during construction (e.g., "Was the cable installed per the ICD specification?") and verifies interface functionality during commissioning (e.g., "Does the SCADA-DCS interface operate as specified?").

Digital Twins and Interface Visualization

Advanced projects are adopting digital twin technology - 3D models that integrate design data from all contractors. Digital twins visualize interfaces spatially, making conflicts obvious.

Example: A digital twin reveals that the SCADA integrator's cable trays clash with the mechanical contractor's pipe routing - a conflict invisible in 2D drawings but obvious in 3D. The PMC identifies and resolves the conflict before fabrication.

Tools: Autodesk BIM 360, Bentley iTwin, Hexagon Smart 3D.

AI-Powered Interface Risk Prediction

Machine learning models trained on historical project data can predict which interfaces are likely to fail, enabling PMCs to allocate resources proactively.

Example: An AI model analyzes the Interface Register and flags IF-023 (SCADA-DCS integration) as high-risk based on patterns: multiple parties, complex protocol, tight schedule, and limited prior experience. The PMC assigns additional engineering support to this interface before problems emerge.

Blockchain for Interface Agreements

Blockchain technology offers immutable, transparent records of interface agreements and deliverable transfers. Smart contracts can automatically trigger payments or penalties based on interface performance.

Example: An Interface Agreement is encoded as a smart contract. When the electrical contractor delivers cable schedules to the SCADA integrator (verified by digital signature), the smart contract releases a milestone payment. If the delivery is late, a penalty is automatically deducted.

Status: Experimental; pilot projects underway in the Middle East and Asia.

Conclusion

Interface risk is the Achilles' heel of multi-contractor projects. Ambiguous responsibilities, information gaps, and coordination failures cascade into delays, cost overruns, and disputes. Yet interface risk is manageable - not through heroic firefighting, but through systematic governance.

Effective PMC governance establishes organizational structures (Interface Managers, Coordinators, RACI matrices), processes and tools (Interface Registers, ICDs, coordination meetings), contractual mechanisms (interface clauses, agreements, incentives), and cultural norms (collaboration, transparency, no-blame reviews) that transform interface management from an afterthought into a core project discipline. The payoff is tangible: projects with robust interface governance consistently outperform peers on schedule, cost, and quality metrics. More importantly, they avoid the late-stage chaos that characterizes poorly coordinated projects - where contractors point fingers, claims proliferate, and the Owner's confidence erodes. For PMCs, interface management is not optional overhead; it is the essence of the value proposition.

About XSAT

XSAT provides Project Management Consultancy (PMC) services for complex oil and gas projects worldwide. Our interface management methodology has been proven across Arctic pipelines, Middle Eastern refineries, and offshore platforms - delivering projects on time, on budget, and with zero interface-related claims.

This briefing reflects industry best practices and field experience as of 2025. Project-specific circumstances may require tailored approaches; consult with qualified PMC professionals when designing interface management strategies.